Safety Advisory Committee

About the Committee

BC Community Information

Construction Alerts

It is a busy summer on the BC campus, here is an update on projects we currently have going on this summer. 

We have a few more construction projects starting over the next couple of weeks.  Some areas of campus will be impacted and closed, please see below. 

 

Completed Projects

       

ONGOING PROJECTS

 

Modernize Room FA-8       5/16 – 7/15/16

Final stages of project, should be completed next week

 

Modernize Room S&E46  6/15/16 – 7/29/16

Project 75% complete and will be completed by 7/29/16

 

Veterans Center Relocation     5/20 – 7/29

No update at this time

 

Addition of Cooling to the Gymnasium 1/20/16 – 8/1/16

Project is in the final stage and will be completed within the next few weeks

 

Modernize of LA Building Rooms 116         5/27/16 – 7/15/16

Asbestos removal, flooring replacement, & painting have been completed, waiting for new furniture to arrive

 

Sports Lighting Project  2/20/16 – 7/15/16

Project is in Final stages and should be completed next week

 

Path or Travel Project       5/23/16 – 9/1/16

Phase 1 of the project is complete, the new concrete has been poured in Phase 2 and they are currently working on the demolition of the final phase.   

 

Science & Engineering & Humanities Roof Repairs        5/31/16 – 7/20/16

The project will involve recoating the roof and will have odor involved.  All coating will take place on Friday & Saturday while the campus is closed.  Please plan accordingly. 

 

Fire Alarm Repairs         6/15/16  - 9/14/16  

There will be some wire pulling done in classrooms and offices but the work should not be very intrusive to our campus.  I will update the schedule as the project progresses

FACE &  Math/Science 6/15 – 6/24

Student Service & Applied Science & Technology:  6/24 – 7/1

Campus Center & LA Building: 7/5 – 7/8

Fine Arts:  7/11 – 7/14

 

Exterior Signage    6/20/16 – 8/5/16

No update as this time

 

District Wide Security Hardware Replacement 7/18/16 – 11/2/16

July 18 – Begin work first floor of the Gym

                  Begin work In Administration Building IT Room. 

July 25 – Begin work on the 2nd floor of the Gym

July 27 – Begin work in the Field House

 

Construction of Facilities, Maintenance, & Operations Building 7/6/16 – 5/30/17

Demolition of the site has begun

 

Warranty work on Pool   8/5/16 -

Scheduled to begin August 5

 

Prop 39 Year 3 exterior light replacement

Project to begin on 7/31/16

Forms


Goals

College Goal 1 - Student Success
Committee Goal:Working to maintain a safe learning and work environment on campus.
College Goal 2 - Professional Development
Committee Goal: Develop a Safety Advisory Team website that can be utilized as a two way communication tool for the committee and community.
College Goal 3: Communication
Committee Goal: Address safety concerns that community members report to our committee. Conduct follow up with the reporting person advising them how their concern was address or will be addressed.
College Goal 4: Facilities & Infrastructure
Committee Goal: Provide information about on going construction on campus by posting information about construction projects on a committee website that will be developed.
College Goal 5: Oversight & Accountability
Committee Goal: Address safety concerns that community members report to our committee. Conduct follow up with the reporting person advising them how their concern was address or will be addressed.

Members

Chair

Members

  • Tim Capehart
  • Anthony Culpepper
  • Zav Dadabhoy
  • Tina Johnson
  • Cheryl Moncier
  • Mary Jo Pasek
  • Jack Pierce
  • Craig Rouse
  • Sheila Shearer
  • Christian Zoller
  • Debra Strong

Student Representatives

  • Elizabeth Gonzales
  • Shay Harleston

Meeting Times

2nd Wednesday, 9-10 a.m.

Last Meeting

Safety Advisory Committee Meeting - December 13th, 2017